HomeEnergyFG Boosts Gombe Power Supply with New Billiri Substation, 400MVA Upgrade

FG Boosts Gombe Power Supply with New Billiri Substation, 400MVA Upgrade

The Federal Government has commissioned a new 120MVA transmission substation in Billiri, Gombe State, and upgraded the Gombe Transmission Substation with two additional transformers, increasing its capacity to distribute electricity to more communities across the North-East.

The projects, commissioned on Thursday, November 19, 2026, by the Minister of Power, Joseph Tegbe, are expected to strengthen electricity transmission, support businesses and improve power supply to households in Gombe and neighbouring areas, including parts of Yobe State.

The new Billiri facility comprises two 60MVA transformers, providing an installed capacity of 120MVA, equivalent to approximately 96MW. It is connected to the existing Gombe–Zabana–Yola transmission line.

Speaking during the commissioning, Tegbe said the project was designed to address longstanding electricity infrastructure challenges affecting Billiri, Numan and adjoining communities.

He stressed that reliable electricity was essential to unlocking the economic potential of the affected areas, supporting businesses, attracting investment and creating employment opportunities.

The minister said the investment reflected President Bola Tinubu’s commitment to strengthening critical electricity infrastructure and ensuring that communities were not denied economic opportunities because of inadequate power supply.

According to him, the project would improve electricity supply within the Jos Electricity Distribution Company (Jos DisCo) franchise area and support increased productive activities.

Tegbe also urged residents to protect the facility against vandalism, warning that damage to the installations could undermine the benefits of the investment.

“These equipment you have here are your assets. They’ve been built for you and for your use. So I make a great appeal to you. You must take care of these facilities. Keep these facilities safe,” he said.

He commended the Gombe State Government for its partnership with the Federal Government, noting that Governor Muhammadu Inuwa Yahaya’s commitment had helped create an enabling environment for infrastructure investment.

Governor Yahaya, represented by the Commissioner for Energy and Mineral Resources, Sanusi Ahmed Pindiga, thanked President Tinubu for assenting to the Electricity Act 2023.

He said the Billiri substation would benefit host communities and neighbouring states, while urging electricity consumers to avoid wastage.

The traditional ruler of Tangale Chiefdom and Seriki of Billiri, Alhaji Danladi Sanusi Dalandi, also welcomed the project, saying improved electricity supply would support businesses, attract investors and create employment.

He added that reliable power would strengthen healthcare delivery, education and other essential social services in the area.

Gombe Substation Capacity Doubles

After commissioning the Billiri facility, Tegbe proceeded to the Gombe Transmission Substation, where he inaugurated an additional 300MVA, 330/132kV transformer and a new 100MVA, 132/33kV transformer.

The upgrade increased the station’s transmission capacity at the 330kV level from 300MVA to 600MVA, effectively doubling its previous capacity.

The replacement of an existing 30MVA transformer with the new 100MVA unit also increased downstream transformation capacity from 120MVA to 220MVA, equivalent to 176MW.

The additional capacity is expected to improve electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East, including Yobe State.

Tegbe said the upgrade would accommodate growing electricity demand and strengthen power delivery across the region.

In his welcome address, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, said electricity demand in Gombe and surrounding communities had outgrown the previous configuration of the transmission station.

He disclosed that TCN awarded the project in June 2021 and completed it in June 2026.

“The new transformers provide our system operators with greater operational flexibility,” Abdulaziz said.

“At the 330kV level, the station now has increased capacity to wheel more power onward. At the 132/33kV level, the larger unit provides Jos DisCo with increased offtake capacity to serve customers in Gombe.”

The TCN chief urged residents to protect the installations and report vandalism or suspicious activities to security agencies or the nearest TCN office.

He also called on Jos DisCo to maximise the additional capacity by taking more electricity from the transmission network to serve its customers.

The commissioning of the two projects represents a further investment in Nigeria’s transmission infrastructure, with the Federal Government seeking to improve the movement of electricity from the national grid to distribution companies and end-users.