The Transmission Company of Nigeria (TCN) has restored the 132kV Karu–Keffi–Akwanga transmission line after reconstructing three towers that collapsed during heavy rainfall and strong winds earlier in October.

The company said in a statement signed by its management on Wednesday, October 28, 2026, that reconstruction of towers T78, T79 and T80 was completed at 5:31 p.m. that day, restoring the transmission pathway serving the 132/33kV Keffi and Akwanga transmission stations.

The towers collapsed on October 7 following heavy rainfall and strong winds, disrupting the affected transmission line.

TCN said its maintenance crew worked to reconstruct the damaged structures and return the line to service.

The restoration re-establishes the transmission pathway serving the Keffi and Akwanga transmission stations, although TCN did not disclose the amount of electricity being transmitted through the line or provide details of any wider impact on power supply during the outage.

The company reiterated its commitment to maintaining and strengthening Nigeria’s electricity transmission infrastructure to support the reliable and efficient movement of bulk electricity across the country.

The restoration comes as the condition and capacity of transmission infrastructure remain important to the delivery of electricity from the national grid to distribution companies and consumers.